THEEGHAMTOWNTEAM

A30 Runnymede roundabout Egham, improvement scheme

Monday, 10 July 2017 12:37

Scheme overview

The Runnymede Roundabout scheme involves improvements to the layout on all approaches to the roundabout and to the roundabout itself. The scheme will create additional carriageway lanes within some parts of the junction and the creation of a new 'U' turn facility for traffic heading towards Staines upon Thames from the M25 motorway. This facility will allow vehicles to avoid negotiating the main part of the junction. Traffic lights will be installed throughout the junction to control the traffic 24 hours a day which will incorporate controlled crossing facilities for pedestrians and cyclists.

As part of the scheme the existing surface water drainage system will be renewed and upgraded along with the installation of new road signs, fences, safety barriers and footways including a brand new facility around the northern side of the roundabout.

The plans detailing the new road layout can be viewed on the PDF at the bottom of this page.

Dates

Tuesday 13 to Monday 3 July - tree clearance works carried out by our contractor Glendales.

Sunday 9 July - night time road closure of the A30 Egham By-pass in both directions between Runnymede Roundabout and the roundabout junction with the High Street and Tite Hill between the hours of 20:00 and 06:00. In addition temporary traffic management in the form of lane closures around part of the roundabout will be installed to facilitate changes to the lane road markings and installation of a temporary road restraint system.

Monday 10 July - night time works (20:00 to 06:00) under lane closures around the roundabout to facilitate changes to the lane road markings and installation of the temporary traffic management required for the construction works.

Monday 10 July until approximately March 2018 - commencement of the main construction works.  These works are scheduled for completion in early March 2018, subject to weather and operational conditions.

We will be issuing regular updates on this web page as the scheme progresses. Enter your email address below to keep up to date with the Runnymede Roundabout improvement work